Hwy 77/I-10 Utility Extension Project
Scope of Work:
- 16" Potable Water Well
- Water Mains
- Gravity Sanitary Sewer Mains
- Lift Station
- 300,000 Gallon Potable Water Storage Tower
Status: Construction in progress.
Chipley Reclaimed Water
Scope of Work:
Prepare a facilities planning document that identifies the methods that are available to discharge the City’s reclaimed water and identify properties that are available for said use and available for sale and or lease.
Status: Facilities plan to be completed by September 2017

5th Street Drainage Improvements
Scope of Work:
Design and construction of a storm-water pond, associated storm-water piping and storm-water control structures. The project also consists of installing approximately 400 lin ft of reinforced concrete pipe (RCP) to cover an open ditch.
Status: Design Phase in progress

5th Street Milling, Resurfacing & Drainage Improvements Phase I
Scope of Work:
US 90 to Old Bonifay Rd (CR 166) a total of .48 miles will be milled and resurfaced with drainage improvements at the intersection of 5th St. and Old Bonifay Rd.
Status: Construction Completed.
5th Street Milling, Resurfacing & Drainage Improvements Phase II
Scope of Work:
South Blvd to US 90 a total of .52 miles will be milled and resurfaced with drainage improvements at the intersection of 5th St and Forrest Ave.
Status: Design Phase in progress.
Pine Ave Sidewalk
Scope of Work:
Construction of sidewalk along Pine Ave from Usery Rd to Third St.
Status: Construction Completed.
Pals Park Phase VI
Scope of Work:
- Renovate/replace existing playground equipment .
- Renovate/replace baseball & softball fields
- Renovate/replace existing concession stand and restrooms
- Renovate/replace bleachers @ baseball field
- Install new security lighting
- Construct new picnic facilities
Status: Construction in progress.

Pals Park - Phase VII
Scope of Work:
- Renovate/replace existing playground equipment
- Renovate/replace baseball & softball fields
- Renovate/replace existing concession stand and restrooms
- Renovate/replace bleachers @ baseball field
- Install new security lighting
- Construct new picnic facilities
Status: Construction in progress.
Pals Park Phase VIII
Scope of Work:
- Construct new playground equipment
- Construct new picnic pavilion
- New sidewalks
- Renovate existing restrooms
- Renovate playground equipment.
Status: Construction in progress